Monkey Mia Infrastructure Upgrade
Monkey Mia Infrastructure Upgrade
The Monkey Mia Infrastructure Precinct was upgraded in 2012 with the construction of a new waste water treatment plant, replacement of the potable water treatment plant and an upgrade of the power generation plant.
Further upgrades occurred in November 2017 in line with the RAC Monkey Mia Dolphin Resort expansion and upgrade.
Project Development
- Construction of new Waste Water Treatment Plant and further upgrades to cater for increased capacity. Hydraulic capacity increased to 450kL/day
- Replacement of Potable Water Treatment Plant and further upgrades to cater for increased capacity – Storage capacity increased to 750kL
- Upgrade of the Power Generation Plant – Projected peak capacity 488kVa
Project Type
Infrastructure Upgrade
Project Scope
- Design and Development Management
- Statutory approvals
- Aboriginal heritage approvals
- Environmental approvals
- Consultant and Contractor Management
- Commissioning and Handover
Project Value
Stage 1 – $5m
Stage 2 – $800k
Engagement
Stage 1 2012
Stage 2 November 2015
“Development management is the conversion of vision to reality through a clear and achievable strategy and robust delivery throughout the life of the project”